Critical path in PERT -

This question was previously asked in
UKPSC JE Civil 8 May 2022 Official Paper-I
View all UKPSC JE Papers >
  1. is always shortest 
  2. may be longest 
  3. may be shortest 
  4. is always longest 

Answer (Detailed Solution Below)

Option 4 : is always longest 
Free
UKPSC JE CE Full Test 1 (Paper I)
1.8 K Users
180 Questions 360 Marks 180 Mins

Detailed Solution

Download Solution PDF

Explanation:

Critical Path:

  • From the activity network representation, it can be analysed that the minimum time to complete the project is the maximum of all paths from start to finish.
  • So, the longest path will represent the critical path for the network, and it will represent the minimum possible duration required to complete the project.
  • The critical path will be the longest path in the network requiring the maximum amount of time, but it will represent the minimum duration that is required to complete all the activities i.e. completion of a project.
Latest UKPSC JE Updates

Last updated on Mar 26, 2025

-> UKPSC JE Notification for 2025 will be out soon!

-> The total number of vacancies along with application dates will be mentioned in the notification.

-> The exam will be conducted to recruit Junior Engineers through Uttarakhand Public Service Commission. 

-> Candidates with an engineering diploma in the concerned field are eligible. 

-> The selection process includes a written exam and document verification. Prepare for the exam with UKPSC JE Previous Year Papers.

Get Free Access Now
Hot Links: teen patti all games teen patti master apk download teen patti gold real cash