Download Solution PDFWhich of the following is true statement for fixed-speed system for wind power when compared to variable system?
This question was previously asked in
PGCIL DT Electrical 22 Aug 2021 Official Paper (SR II)
Answer (Detailed Solution Below)
Option 1 : Higher reliability
Free Tests
View all Free tests >
PGCI DT EE Power System Mock Test
6.1 K Users
20 Questions
20 Marks
15 Mins
Detailed Solution
Download Solution PDFAdvantages of fixed-speed speed over Variable system for wind power
- The construction of fixed speed wind turbine is simple, robust, and reliable.
- Cost of the electrical part is low.
- The variable speed system is somewhat more complex than the fixed speed system.
- No frequency conversion hence no current harmonics.
Last updated on May 9, 2025
-> PGCIL Diploma Trainee result 2025 will be released in the third week of May.
-> The PGCIL Diploma Trainee Answer key 2025 has been released on 12th April. Candidates can raise objection from 12 April to 14 April 2025.
-> The PGCIL DT Exam was conducted on 11 April 2025.
-> Candidates had applied online from 21st October 2024 to 19th November 2024.
-> A total of 666 vacancies have been released.
-> Candidates between 18 -27 years of age, with a diploma in the concerned stream are eligible.
-> Attempt PGCIL Diploma Trainee Previous Year Papers for good preparation.