In case of well foundation, grip length is defined as the

This question was previously asked in
BPSC AE Paper V Civil 19 Dec 2024 Official Paper
View all BPSC AE Papers >
  1. Length below the top of the well cap to the cutting edge
  2. Length between the bottoms of the well cap to the cutting edge
  3. Depth of the bottom of the well below the maximum scour level
  4. Depth of the bottom of the well below the minimum scour level

Answer (Detailed Solution Below)

Option 3 : Depth of the bottom of the well below the maximum scour level
Free
BPSC AE सामान्य हिंदी Mock Test
2.6 K Users
20 Questions 40 Marks 24 Mins

Detailed Solution

Download Solution PDF

Explanation:

  • Grip length refers to the embedment depth of the well below the maximum scour level.

  • It is the depth provided to ensure stability of the well foundation against:

    • Overturning

    • Sliding

    • Uplift

    • Lateral loads (especially in bridge foundations)

  • Scour is the removal of soil around a foundation due to flowing water.

  • The maximum scour level represents the lowest level the riverbed may reach due to extreme flow conditions.

  • The well must penetrate below this level to remain stable even during floods.

 Additional Information

Well Foundation: A deep foundation type used mostly for heavy loads, especially for bridges, piers, and waterfront structures. It consists of a large-diameter hollow cylindrical well sunk into the ground to a suitable depth.

  • The cutting edge is the sharp bottom edge of the well, designed to cut through soil or rock during sinking.

Grip length is important because:

  • It provides skin friction between the well’s cylindrical surface and the surrounding soil, enhancing stability.

  • It resists uplift and lateral loads acting on the foundation.

  • Ensures that the well foundation remains stable under various load conditions, including scour and soil movement.

Sinking process: The well is gradually sunk by excavating soil inside the well or by adding weights, and the cutting edge helps penetrate the soil or rock below.

Design considerations include:

  • Grip length should be sufficient to provide adequate friction and prevent sliding.

  • The length also affects the settlement and bearing capacity of the foundation.

  • Must consider scour depth if located in water bodies; foundation depth should be below maximum scour level to prevent exposure.

Latest BPSC AE Updates

Last updated on Jul 17, 2025

-> BPSC AE exam analysis 2025 is available now. 

-> BPSC AE admit card 2025 has been released at the official website.

-> BPSC AE 2025 exam date has been revised. The exam will be conducted on July 17, 18 & 19 now. 

-> Candidates who were facing technical issues while filling form can now fill the BPSC AE application form 2025 without any issue. 

->BPSC AE age limit 2025 has been revised. Also Check the BPSC AE Syllabus and Exam Pattern

->BPSC AE application form 2025  was released on April 30. The last date to fill BPSC AE form 2025 was May 28. 

->BPSC AE interview call letters released for Advt. 32/2024.

->BPSC AE notification 2025 has been released. 

->A total of 1024 vacancies are announced through BPSC AE recruitment 2025

->The BPSC Exam Calendar 2025 has been released for the Assistant Engineer Recruitment.

-> The selection will be based on a written exam and evaluation of work experience.

-> Candidates with a graduation in the concerned engineering stream are eligible for this post.

-> To prepare for the exam solve BPSC AE Previous Year Papers. Also, attempt the BPSC AE Civil  Mock Tests.

More Deep Foundation Questions

Get Free Access Now
Hot Links: all teen patti master teen patti cash game teen patti sweet teen patti bliss