Question
Download Solution PDFWhen float or slack of an activity is positive:
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
Slack of an activity
- It is the difference between the Earliest Start time and Latest Finish time.
- If the Slack of any activity is positive then it means that resources are surplus and the project is not delayed.
- If the slack of an activity is negative then it means that resources are lacking and the project will be delayed and will not be completed on the time, additional resources are required to complete the project.
- If the slack of an activity is zero then resources are just enough to complete the project and the project will be completed on time, this type of activity is critical any delay in this activity will delay the project completion by the same time.
Last updated on May 19, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been released on its official website.
-> JKSSB JE exam will be conducted on 10th August (Civil), and on 27th July 2025 (Electrical).
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from18th May 2025 to 16th June 2025
-> Candidates who are preparing for JKSSB JE can download syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.